Ivanpah Project News
 

Ivanpah Update

Welcome to Update from Ivanpah - the newsletter of BrightSource Energy – published periodically to keep you updated on the latest project developments from the Ivanpah Solar Electric Generating System (ISEGS). 


  1. Update from Ivanpah - May 2013

    Ivanpah Project Is More Than 92 Percent Complete

    As the Ivanpah project nears completion, the team continues to move full steam ahead. During the months of February, March and April, more than 1,250 construction workers advanced the project to more than 92 percent complete! To date, more than 153,990 of the project’s total 173,500 heliostats have been installed. Several stunning photos below show recent progress at the site. For a slideshow of all the new photos, click here.

    Read more
  2. Update from Ivanpah - August 2012

    • Ivanpah Reaches Halfway Mark and Peak of Construction Employment
    • Significant Solar Field Progress
    • Construction Update
    • Ivanpah Hosts Media Visitors
    • President Clinton makes a visit

    Read more